PROJECTS EXECUTED/IN HAND
Turnkey Projects
Sewage /EffluentTreatment
Plants & Sewerage system |
Back |
S.N. |
Description
of work |
Client |
Contract value
(Rs lacs)
|
Remarks |
1.
|
10
MLD STP at Vasantkunj Delhi
|
BAPL/
DWS & SDU ( now DJB)
|
71
|
Work
Completed
|
2. |
1.0
+ 0.2 MLD STPs at Dibiyapur township,UP
|
GAIL,
Delhi
|
96
|
Work
Completed
|
3.
|
1.0
MLD STP at Reckong Peo, HP
|
IPHD,
Rampur, HP
|
52
|
Work
Completed
|
4.
|
0.53
MLD STP at Satellite township,
|
SAIL,
Ranchi
|
75
|
Work
Completed
|
5.
|
8.0
MLD STP, FAB at Rewari, Haryana
|
PHED,
Haryana
|
140
|
Work
Completed
|
6.
|
22
MLD STP, UASB, at Chehedi, Nasik
|
Nasik
Municipal Corporation
|
475
|
Work
completed
|
7.
|
12
MLD STP, UASB at Bhamori, Indore
|
PHED,
Indore, MP
|
357
|
Work
Completed
|
8.
|
3.0 MLD STP
and Sewerage system, pumping, at KDH
town
|
CCL, Ranchi, World Bank
|
163
|
Work Completed
|
9.
|
3.0
MLD STP and Sewerage system,
pumping at Parej town
|
CCL,
Ranchi, World Bank
|
135
|
Work
Completed
|
10. |
1.5
MLD STP - recycle plant at Ambala cantt, |
Cantonment
board, Ambala Haryana |
|
Work
Completed
|
11. |
675
m3/d ETP, at Kakkancherry,Calicut |
KINFRA,
Kerala, MACL, Mumbai |
|
Work
Completed
|
12. |
Sewerage system
at Khanna town, part-II, |
PWSSB, Ludhiana |
189
|
Work in Progress |
13. |
Sewerage system
at Khanna town, part-III, |
PWSSB, Ludhiana |
939
|
Work in Progress |
14. |
Sewerage system
at Kapurthala |
PWSSB, Jalandhar |
199
|
Work in Progress |
15. |
Sewerage system
at Kartarpur |
PWSSB, Jalandhar |
96
|
Work in Progress |
16. |
Sewerage system
at Dhuri-I, Sangrur |
PWSSB, Sangrur |
162
|
Work in Progress |
17. |
Sewerage system
at Ahmedgarh-I, Sangrur |
PWSSB, Sangrur |
195
|
Work in Progress |
18. |
Sewerage system
at Malerkotla-I, Sangrur |
PWSSB, Sangrur |
152
|
Work in Progress |
19. |
Sewerage system
at Jagraon, Ludhiana |
PWSSB, Ludhiana |
648
|
Work in Progress |
20. |
Sewerage system
at Banga, Nawanshahar |
PWSSB, Hoshiarpur |
164
|
Work in Progress |
|
|
Top
|
|
|
|